SOU

SOU 40.1-31032472-11:2009
SOU 40.1-31032472-11:2009
Requirements for the design of cable lines up to 10,000 V using flexible corrugated two-layer polyethylene pipes. setting
SOU 40.1-31032472-12:2009
SOU 40.1-31032472-12:2009
Installation of cable lines up to 10,000 V using flexible corrugated double-layer polyethylene pipes. instruction
SOU 40.1-31032472-13:2009
SOU 40.1-31032472-13:2009
Operation of cable lines up to 10,000 V using flexible corrugated two-layer polyethylene pipes. instruction
SOU 45.2-31032472-10:2009
SOU 45.2-31032472-10:2009
Cable lines up to 10,000 V using flexible corrugated double-layer polyethylene pipes. design
SOU D 2.2-34717706-001:2009
SOU D 2.2-34717706-001:2009
Resource base unit cost indexes for construction works. Motor ways. Traffic safety.
SOU D 2.2-34717706-002:2009
SOU D 2.2-34717706-002:2009
Resource estimates for operation of construction machines and mechanisms. Motor ways. Traffic safety.
SOU D 2.2-35683453-001:2009
SOU D 2.2-35683453-001:2009
Resource base unit cost indexes for construction works. Piling works. Installation of reinforced concrete bored piles in stable soils of group I-V using universal drilling rig BG-40.
SOU D 2.7-35683453-002:2009
SOU D 2.7-35683453-002:2009
Resource estimates for operation of construction machines and mechanisms. Piling works. Universal drilling rig for installation of bored piles BG-40.
SOU D.2.2-05408668-001:2009
SOU D.2.2-05408668-001:2009
Resource base unit cost indexes for construction works. Motor ways.
SOU D.2.2-13-2.5-10:2009
SOU D.2.2-13-2.5-10:2009
Resource base unit cost indexes for construction works. Restoration of steel pipelines with the diameter of 1220-2800mm using mobile units.
SOU D.2.2-20057315-003:2009
SOU D.2.2-20057315-003:2009
Resource base unit cost indexes for construction works. Piling works. Installation of bored piles with the diameter of 300 mm in stable soils of groups I-II using the drilling rig MusTang 5-P4.
SOU D.2.2-25272797-001:2009
SOU D.2.2-25272797-001:2009
Resource base unit cost indexes for construction works. Trenchless laying of metal pipes by plugging using the mechanism SO-166m.
SOU D.2.2-25-PR2:2009
SOU D.2.2-25-PR2:2009
Laying pipelines with a diameter of up to 600 mm using horizontal directional drilling using Robbins HDD UNI 36x50
SOU D.2.2-30645586-001:2009
SOU D.2.2-30645586-001:2009
Resource base unit cost indexes for construction works. Motor ways.
SOU D.2.2-31256895-001:2009
SOU D.2.2-31256895-001:2009
Resource base unit cost indexes for construction works. Motor ways.
SOU D.2.2-32287238-001:2009
SOU D.2.2-32287238-001:2009
Resource base unit cost indexes for construction works. Earth works
SOU D.2.2-33498333-001:2009
SOU D.2.2-33498333-001:2009
Resource base unit cost indexes for construction works. Mesh structures.
SOU D.2.2-34850918-001:2009
SOU D.2.2-34850918-001:2009
Resource base unit cost indexes for construction works. Motor ways.
SOU D.2.2-5-20057315-002:2009
SOU D.2.2-5-20057315-002:2009
Resource base unit cost indexes for construction works. Installation of reinforced concrete bored piles with the diameter of 1020 mm in unstable saturated soils of group 2 using rotor hydraulic drill rig with the capacity of 300 kW.
SOU D.2.2-5-32129970-001:2009
SOU D.2.2-5-32129970-001:2009
Resource base unit cost indexes for construction works. Piling works. Installation of augercast piles with the length up to 30 m in soils of group II using self-propelled drilling rigs IPC DRILL 830 BB and automated cementing units IPC G.
SOU D.2.2-5-4:2009
SOU D.2.2-5-4:2009
Resource base unit cost indexes for construction works. Piling works. Installation of reinforced concrete bored piles in stable soils of group 1-2 using universal drilling rigs Bauer BG -36.
SOU D.2.4-20-3A-2009
SOU D.2.4-20-3A-2009
Resource base unit cost indexes for construction and repair works. Anti-corrosive protection of internal surfaces of turbine condensers at nuclear power plants.
SOU D.2.7-01386326-002:2009
SOU D.2.7-01386326-002:2009
Resource estimates for operation of construction machines and mechanisms. Static tower crane TEREX COMEDIL CTL 180-16 TS23.
SOU D.2.7-03450620-001:2009
SOU D.2.7-03450620-001:2009
Resource estimates for operation of construction machines and mechanisms. Motor ways.
SOU D.2.7-20057315-001:2009
SOU D.2.7-20057315-001:2009
Resource estimates for operation of construction machines and mechanisms. Excavators. Equipment for well boring and dewatering, cementing equipment. Pile driving rigs.
SOU D.2.7-20057315-004:2009
SOU D.2.7-20057315-004:2009
Resource estimates for operation of construction machines and mechanisms. Piling works.
SOU D.2.7-24155428-001:2009
SOU D.2.7-24155428-001:2009
Resource estimates for operation of construction machines and mechanisms. Caterpillar fully mobile cranes MANITOWOC 15000 with the lift capacity of 250 tons. Cranes on special truck-like chassis GROVE GMK 6300L with the lift capacity of 300 tons.
SOU D.2.7-30645586-002:2009
SOU D.2.7-30645586-002:2009
Resource estimates for operation of construction machines and mechanisms. Motor ways.
SOU D.2.7-32129970-002:2009
SOU D.2.7-32129970-002:2009
Resource estimates for operation of construction machines and mechanisms. Self-propelled drilling rigs IPC DRILL 830 BB, bore diameter up to 300mm. Automated cementing units IPC GI ЭT 8 with the capacity of 8 m3 /h
SOU D.2.7-32287238-002:2009
SOU D.2.7-32287238-002:2009
Resource estimates for operation of construction machines and mechanisms. Earth works.
SOU D.2.7-33-2.5-09:2009
SOU D.2.7-33-2.5-09:2009
Resource estimates for operation of construction machines and mechanisms.
SOU D.2.7-3A-2009
SOU D.2.7-3A-2009
Resource estimates for operation of construction machines and mechanisms.
SOU D.2.7-5:2009
SOU D.2.7-5:2009
Resource estimates for operation of construction machines and mechanisms. Drilling rig Bauer BG -36 with the capacity of 150 kW.
SOU ZhKG 75.11-35077234.0015:2009
SOU ZhKG 75.11-35077234.0015:2009
Residential buildings. Rules for determining the physical deterioration of residential buildings
SOU ZhKG 75.11-35077234.0016:2009
SOU ZhKG 75.11-35077234.0016:2009
Residential buildings. Collection of aggregate indicators of the cost of recreating high-rise residential buildings
SOU-N BD.1.1-0121844-1:2009
SOU-N BD.1.1-0121844-1:2009
Instructions on the use of base unit cost indexes for construction, repair and construction works and installation of equipment at Zaporozhye NPP.

All Codes and Regulations

All Categories

Send us a message Expand Collapse

Leave your message in the form below, and we will write back by e-mail!